Motorists, be aware. The following is a list fo the highway projects from the Colorado Department of Transportation planned for this week across Southern Colorado.
Officials said all work is dependent upon the weather.
I 25 Northbound/Southbound at US 50/CO 47 in Pueblo
(Milemarker 100) (through January 2013)
7:00 AM-5:00 PM MO-FR Single lane closures in both directions on I-25 and in both directions on US 50 for seeding operations 7a-5p. In addition, various ramps at the interchange will be closed throughout the day. SA, 1/19/12, half the ramp from US 50/SH 47 to northbound I-25 will be closed midnight to 7pm for water line repair. Delays possible.
US 350 Eastbound/Westbound Nine Miles East of Trinidad
(Milemarker 8.4-8.7) (through July 2013)
24 Hours- There will be one lane alternating traffic beginning 1/16/13 with flaggers and temporary traffic signals 24 hours a day for bridge replacement. Project hotline - 719-431-9595. Delays possible.
US 85 Northbound/Southbound Between Cook Ranch and just north of Louviers
(Milemarker 193-197) (through July 2013)
8:00 AM-4:30 PM MO-FR Short term lane closures with flaggers at Ron King Rd to allow equipment to cross the highway. Minimal delays.
CO 21 Northbound/Southbound Powers Boulevard Between Woodmen Road and E. Milton
Proby Parkway (Milemarker 140.5) (through January 2013)
8:00 AM-5:00 PM MO-FR Shoulder closures only in both directions on Powers from Constitution to Barnes for shoulder work. No delays expected.
CO 239 Northbound/Southbound One Mile North of Trinidad
(Milemarker 1) (through April 2013)
24 Hours- There will be one lane alternating traffic 24/7 for duration of project beginning TH, 1/3/12. Traffic signals will regulate traffic. 14 ft width restriction in effect from 1/3/12 through 4/2013. Delays possible.
CO 266 Eastbound/Westbound East of Rocky Ford
(Milemarker 2.64) (through April 2013)
7:00 AM-5:00 PM MO-FR There will be one lane alternating traffic for bridge replacement project. No closures will take place on Tuesday. Speed limit reduced to 35 mph. 10 minute delays.
CO 71 Northbound/Southbound North of Rocky Ford
(Milemarker 19.27) (through April 2013)
24 Hours- Traffic placed on detour route for bridge replacement through completion of project. Delays possible.
Speed limit reduced to 45 mph through detour. 12 ft. width restriction in effect.